Roadmap to unlock Australia's onshore wind pipeline 

Publication Date
17 November 2026

A new Infrastructure Australia analysis has found that without coordinated national action, delivery of Australia’s onshore wind generation is at risk, as our ports and roads struggle with the mammoth freight task of transporting thousands of giant wind turbines across the country.  

An audit analysing the freight task required to deliver Australia’s onshore wind pipeline has found current demand over the next several years may exceed the capacity of some of the nation’s most critical ports and freight corridors.  

Without a coordinated approach between the Australian, state and territory governments, as well as investment in enabling infrastructure and regulatory reform, this demand could risk delivery delays, cost increases and impacts on communities as Australia races to meet its net zero ambitions, Infrastructure Australia CEO Adam Copp said. 

“This report gives a clear, practical plan for delivering the freight task behind Australia's onshore wind pipeline,” Mr Copp said. 

“We’re talking about moving blades that are about as long as the Statue of Liberty, or more than double the length of a Boeing 737. 

“Onshore wind is a critical pillar of the clean energy transition. So we need to get this right. 

“Just as critical is social licence – we need to make sure we bring the community along with us and not only minimise any impacts but ensure we leave a lasting positive legacy of better local infrastructure and economic benefit. 

“This report lays out the roadmap to deliver the energy transition more efficiently, at reduced cost, and with potential to create new local manufacturing opportunities for wind turbine components as well.” 

The report, Enabling Infrastructure for the Energy Transition, analysed 56 onshore wind projects expected to start construction by 2030, representing approximately 30 gigawatts of planned generation capacity. 

These will require more than 4,500 turbines to be imported and transported from ports to project sites, involving an estimated 62,000 over-size, over-mass (OSOM) vehicle movements by 2030.  

When it comes to major freight routes, Infrastructure Australia’s audit found more than 900 route constraints across the road network, many involving complex bridge, height and port access issues. 

“This is a national productivity challenge that requires a coordinated national response,” Mr Copp said. 

“This task has outgrown a project-by-project approach. Each of these projects has been planning its own port, its own route and its own approvals in isolation. What this report shows is that when you add up the demand across the whole pipeline, it exceeds what our ports and roads can actually handle at peak times. 

“The scale and pace of the demand for onshore wind, and the ever-increasing dimensions of these huge turbines, will put substantial pressure on infrastructure systems.  

“Road corridors and bridges that were never designed for this – we’ve already seen this play out with a giant turbine component becoming stuck under a bridge in Queensland recently, causing chaos on the Warrego Highway, and in Ararat, Victoria, where a 70-metre-long wind turbine blade caused traffic disruptions and damage through residential streets.  

“Ports, roads, heavy vehicle pilots, escorts and drivers all need to line up at the same time for a single turbine to move, and right now the settings that govern that process are inconsistent between states.” 

Mr Copp said progress was being made since these constraints were uncovered by the audit. 

“We’ve proposed a range of regulatory reforms to solve this challenge as well as several investment opportunities which we’ve listed on our 2026 Infrastructure Priority List - our independent, evidence-based advice to the Australian Government on the highest priority, nationally significant proposals that should be considered for investment over the next 10 years. 

“Recently, we saw the Australian and NSW governments announce more than $1.74 billion for upgrades across three regional NSW road corridors which were identified by our audit. 

“We’re also working closely with our partners across the Australian, state and territory governments, including the National Heavy Vehicle Regulator, who are already taking action on these issues.” 

To read more about the report visit infrastructureaustralia.gov.au.