Infrastructure Priority List

Port Botany Rail Line Duplication and Cabramatta Passing Loop

Port Botany Rail Line Duplication and Cabramatta Passing Loop

Infrastructure Australia | Infrastructure Priority List |

Port Botany Rail Line Duplication and Cabramatta Passing Loop

PROJECT STAGE
EARLY STAGE PROPOSAL
EARLY STAGE PROPOSAL
EARLY STAGE PROPOSAL
POTENTIAL INVESTMENT OPTIONS
POTENTIAL INVESTMENT OPTIONS
POTENTIAL INVESTMENT OPTIONS
INVESTMENT READY PROPOSAL
INVESTMENT READY PROPOSAL
INVESTMENT READY PROPOSAL
PROJECT DELIVERY
PROJECT DELIVERY
PROJECT DELIVERY
PROJECT DELIVERY
POST COMPLETION REVIEW
LOCATION
Sydney, NSW
SECTOR
Transport
PROPONENT
Australian Rail Track Corporation (ARTC)
PRIORITY LIST STATUS
Previously listed
EVALUATION HISTORY
Planning Investment (Problem Identification) - 21/12/2015
Delivery Investment (Business Case) - 20/02/2020
Map showing NSW

The proposal comprises the duplication of the remaining single-track section of the Port Botany Rail Line, and delivery of a new passing loop on the Southern Sydney Freight Line, to increase capacity, efficiency and reliability.

The business case was accepted for Infrastructure Australia's evaluation on 2nd August, 2019.

On 20 February 2020, the Port Botany Rail Line Duplication Project was added to the Infrastructure Priority List as a Priority Project.